Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

\"I think we goofed when we hired that new assistant controller,\" said Ruth Sca

ID: 2477065 • Letter: #

Question

"I think we goofed when we hired that new assistant controller," said Ruth Scarpino, president of Provost Industries. "Just look at this report that he prepared for last month for the Finishing Department. I can't understand it Finishing Department costs Work in process inventory, April 1, 9,000 units $31,850* materials 100% complete: conversion 60% complete Costs transferred in during the month from the preceding department, 135,000 units Materials cost added during the month Conversio 267,530 56,500 242,392 n costs incurred during the month Total departmental costs $598,272 Finishing Department costs assigned to Units completed and transferred to finished goods 120,000 units at $4.986 per unit $598,272 Work in process inventory, April 30, 24,000 units materials 0% complete conversion 40% complete Total departmental costs assigned $598,272 *Consists of cost transferred in, $8,950; materials cost, $3,500; and conversion costs, $19,400 He's struggling to learn our system," replied Frank Harrop, the operations manager. "The problem is that he's been away from process costing for a long time, and it's coming back slowly." "It's not just the format of his report that I'm concerned about. Look at that $4.986 unit cost that he's come up with for April. Doesn't that seem high to you?" said Ms. Scarpino "Yes, it does seem high; but on the other hand, I know we had an increase in materials prices during April, and that may be the explanation," replied Mr. Harrop. "T'l get someone else to redo this report and then we may be able to see what's going on. Provost Industries manufactures a ceramic product that goes through two processing departments- Molding and Finishing. The company uses the weighted-average method in its process costing

Explanation / Answer

Answer: 1 a)

Equivalent units = Units transferred + units in ending WIP * % of completion using the same

Equivalent units for transferred in = 120000 + 24000 = 144000 units

Equivalent units for material = 120000 + 24000 * 0% = 120000 units

Equivalent units for conversion = 120000 + 24000*40% = 120000+9600 = 129600 units

Calculation of Cost per equivalent unit:

Transferred in = (8950+267530) / 144000 = $1.92 per unit

Material= (3500+56500)/120000 = $0.5 per unit

Conversion = (19400+242392)/129600 = $2.02 per unit

Answer: 1 b)

Calculation of cost of ending WIP:

Transferred in = 24000*$1.92 = $46080

Material = 0*$0.5 = $0

Conversion = 9600*$2.02 = $19392

Total = $46080+$0+$19392= $65472

Answer:1 c)

Calculation of costs of units transferred and completed:

Transferred in = 120000*$1.92 =$230400

Material = 120000*$0.5 = $60000

Conversion = 120000*$2.02 = $242400

Total = $230400+$60000+$242400= $532800