Swasey Fabrication, Inc., manufactures frames for bicycles. Each frame passes th
ID: 2480791 • Letter: S
Question
Swasey Fabrication, Inc., manufactures frames for bicycles. Each frame passes through three processes: Cutting, Welding, and Painting. In September, the Cutting Department of the Tulsa, Oklahoma, plant reported the following data: 1. In Cutting, all direct materials are added at the beginning of the process. 2. Beginning work in process consisted of 40,500 units, 20 percent complete with respect to direct labor and overhead. Costs in beginning inventory included direct materials, $1,215,000; direct labor, $222,600; and applied overhead, $150,000. 3. Costs added to production during the month were direct materials, $2,565,000; direct labor, $3,471,150. Overhead was assigned using the following information: Activity Rate Actual Driver Usage Inspection $150 per inspection hour 4,000 inspection hours Maintenance $750 per maintenance hour 1,600 maintenance hours Receiving $300 per receiving order 2,000 receiving orders 4. At the end of the month, 121,500 units were transferred out to Welding, leaving 13,500 units in ending work in process, or 25 percent complete. Required: 1. Prepare a physical flow schedule. 2. Calculate the equivalent units of production schedule under weighted average method for direct materials and conversion costs. 3. Compute unit cost under weighted average. 4. Calculate the cost of goods transferred to Welding at the end of the month. Calculate the cost of ending inventory. 5. Prepare the journal entry that transfers the goods from Cutting to Welding.
Explanation / Answer
Working Notes:
1) Physical flow
Note: strated and completed = transferred out - beginning WIP
2)
3)
4)
5)
Work in process-Welding.............................Dr. $9477000
Work in process- Cutting ..................................................Cr. $9477000
Activity Rate ($) Actual Usage Activity Cost ($) Inspection 150 per inspection hours 4000 hours 600000 Maintenance 750 per maintenance hours 1600 hours 1200000 Receiving 300 per receiving order 2000 hours 600000 Total overhead cost assigned 2400000Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.