Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: 0.6 days 15.3 days Inspection time Wait time (from order to start of production) Process time Move time Queue time 3.4 days 0.9 days 3.6 days Required: 1. Compute the throughput time. (Round your answer to 1 decimal place.) Throughput time days Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.) 2. Manufacturing cycle efficiency

Explanation / Answer

Manufacturing Cycle Efficiency (MCE) = Value-Added time/Manufacturing Cycle Time

1) Throughput Time = process time + inspection time + move time+ Queue time = 3.4 + 0.6+ 0.9+ 3.6 = 8.5 days 2. Manufacturing cycle efficiency

Manufacturing Cycle Efficiency (MCE) = Value-Added time/Manufacturing Cycle Time

= (3.4+0.6)/8.5 =47% 3) Non value added activities = (0.9+3.6)/8.5 = 53% 4) Delivery Cycle time =Throughput time + wait time = 8.5 +15.3 = 23.8 days 5. New MCE Through put time = 8.5 -3.6= 4.9 days MCE = 4/4.9 = 82%