A document in a job order costing system that is used to record the costs of producing a job is a(n): Job cost sheet. Job lot. Finished goods summary. Process cost system. Units-of-production sheet. Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,500 of direct materials and used $4,000 of direct labor. The job was not finished by the end of the month, but needed an additional $3,000 of direct materials and additional direct labor of $6,500 to finish the job in October. The company applies overhead at the end of each month at a rate of 200% of the direct labor cost incurred. What is the total cost of the job when it is completed in October?Explanation / Answer
28) Job cost sheet is used to record the cost of producing a job.*
29) Total cost of job A3B= 2500+4000+3000+6500+200%*(4000+6500)=37000
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.