Consider the following data collected for Great Homes Inc.: Requirement Compute
ID: 2483921 • Letter: C
Question
Consider the following data collected for Great Homes Inc.: Requirement Compute the price, efficiency, and flexible-budget variances for direct materials and direct manufacturing labour. Requirement. Compute the price, efficiency, and flexible-budget variances for direct materials. Label each variance as favourable (F) or unfavourable (U). Price variance Efficiency variance Flexible-budget variance Compute the price, efficiency, and flexible-budget variances for direct manufacturing labour. Label each variance as favourable (F) or unfavourable (U). Price variance Efficiency variance Flexible-budget varianceExplanation / Answer
Material price variance = (standard price-actual price) * actual quantity
= (standard price*actual quantity)-(actual price * actual quantity)
= 214000-200000
= F14000
Material efficiency variance = (actual quantity-standard quantity)*standard price
= (actual quantity*standard price)-(standard quantity*standard price)
=(214000)-(225000)
= -11000
=11000F
Flexible budget variance = standard material cost-actual material cost
= 225000-200000
=25000F