Lead Time The Snow Glide Ski Company manufactures skis in the finishing and asse

ID: 2489981 • Letter: L

Question

Lead Time The Snow Glide Ski Company manufactures skis in the finishing and assembly process. Skis are manufactured in 40-ski batch sizes. The finishing time is 16 minutes per ski. The assembly time is 12 minutes per ski. It takes 15 minutes to move a batch of skis from finishing to assembly. a. Compute the value-added, non-value-added, and total lead time of this process. Value-added lead time 28 minutes Non-value-added lead time minutes Total lead time minutes b. Compute the value-added ratio. Round to one decimal place. %

Explanation / Answer

a. Value-added lead time = 16 + 12 = 28 minutes

Non-value-added lead time = 15 minutes

Total lead time = 28 + 15 = 43 minutes

b. the value-added ratio = 28 / 43 = 65.12%.