Question 2 During 2014, Antoinette started a construction job with a contract pr
ID: 2490032 • Letter: Q
Question
Question 2 During 2014, Antoinette started a construction job with a contract price of $2.8 million. The job was completed in 2016 and information for the three years of construction is as follows:
2014 2015 2016
Costs incurred to date $1,230,000 $1,765,000 $1,965,000
Estimated costs to complete 850,000 175,000 –0–
Billings to date 1,000,000 1,880,000 2,800,000
Collections to date 710,000 1,720,000 2,800,000
Calculate the amount of gross profit / (loss) that should be recognized each year under the percentage-of-completion method. (Round percent complete to 2 decimal places, e.g. 52.75%. Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)
Under the earnings approach:
Explanation / Answer
$ Particulars 2014 2015 2016 Costs incurred to date 1,230,000 1,765,000 1,965,000 Estimated costs to complete 850,000 175,000 - Total Cost 2,080,000 1,940,000 1,965,000 percentage-of-completion 59.13% 90.98% 100% (Costs incurred to date/Total cost Contract price 2,800,000 2,800,000 2,800,000 Revenue to be recognised 1,655,769 2,547,423 2,800,000 (Contract price*percentage-of-completion) Costs incurred to date 1,230,000 1,765,000 1,965,000 Profit or loss to be recognised(Cummulative) 425,769 782,423 835,000 Profit or loss to be recognised in each year 425,769 356,653 52,577 (782422-425769) (835000-782423)
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.