Problem 3-18A Contrasting Activity-Based Costing and Conventional Product Costin
ID: 2493037 • Letter: P
Question
Problem 3-18A Contrasting Activity-Based Costing and Conventional Product Costing [LO3-2, LO3-3, LO3-4]
[The following information applies to the questions displayed below.]
Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company’s five activity cost pools:
Activity Cost Pool
Activity
Measure
Expected
Overhead Cost
Expected
Activity
Labor-related
Direct labor-hours
$
57,000
9,500
DLHs
Purchase orders
Number of orders
$
13,500
4,500
orders
Material receipts
Number of receipts
$
12,000
1,000
receipts
Relay assembly
Number of relays
$
28,000
3,500
relays
General factory
Machine-hours
$
252,000
36,000
MHs
Problem 3-18A Part 1
+
Problem 3-18A Part 2
Using the ABC data, determine the total amount of overhead cost assigned to each product.
+
Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company’s five activity cost pools:
Explanation / Answer
Activity cost pool Activity Measure Expected cost($) Expected act, Act. Rate Labor- related Direct Labour- Hr 57000 9500 6 Purchase order Number of orders 13500 4500 3 material receipt Number of receipts 12000 1000 12 Relay assembly Number of relays 28000 3500 8 General Factory Machine Hours 252000 36000 7 Ans2 Activity based costing Product A Product B ProductC ProductD Purchase order 350*3=1050 600*3=1800 2475*3=7425 1075*3=3225 material receipt 330*12=3960 160*12=1920 510*12=6120 0*12=0 Relay assembly 220*8=1760 220*8=1760 1575*8=12600 1485*8=11880