QUESTION 23 Landram Corporation makes a product with the following standard cost
ID: 2495164 • Letter: Q
Question
QUESTION 23
Landram Corporation makes a product with the following standard costs:
Inputs
Standard Quantity or Hours
Standard Price or Rate
Direct materials
2.0 kilos
$7.00 per kilo
Direct labor
1.4 hours
$10.00 per hour
Variable overhead
1.4 hours
$4.00 per hour
In March the company produced 4,800 units using 10,320 kilos of the direct material and 2,300 direct labor-hours. During the month, the company purchased 10,890 kilos of the direct material at a cost of $76,770. The actual direct labor cost was $38,242 and the actual variable overhead cost was $11,943.
The company applies variable overhead on the basis of direct labor-hours. The direct materials price variance is computed when the materials are purchased.
The materials price variance for March is: (Do not round intermediate calculations.)
$540 F
$400 U
$400 F
$540 U
7 points
QUESTION 24
Niemiec Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below:
Hour
Move time
2.3
Wait time
19.3
Queue time
11.4
Process time
1.3
Inspection time
0.9
The manufacturing cycle efficiency (MCE) was closest to: (Round your intermediate calculation and final answer to 2 decimal places.)
0.02
0.08
0.92
0.16
Landram Corporation makes a product with the following standard costs:
Explanation / Answer
The materials price variance for March is: (Do not round intermediate calculations.) A. $540 F B. $400 U C. $400 F D. $540 U 7 points Material Price Variance = (Standard Cost - Actual Cost per unit) X Actual units purchased Actual Cost per unit = 7.049587 Therefore, Material Price Variance = (7 - 7.04) * 10890 435.6 U The amount which is closest to this is 400 U and hence B is the correct alternative. QUESTION 24 Niemiec Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below: Hour Move time 2.3 Wait time 19.3 Queue time 11.4 Process time 1.3 Inspection time 0.9 The manufacturing cycle efficiency (MCE) was closest to: (Round your intermediate calculation and final answer to 2 decimal places.) A. 0.02 B. 0.08 C. 0.92 D. 0.16 Manufacturing Cycle Efficiency = Value Added Time/Manufacturing Cycle Time Hence, in this case Value Added Time 2.2 Manufacturing Cycle Time 33 Hence, the MCE will be 0.066666667 Since this is closest to 0.08, hence B is the correct solution.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.