Below is the Bill of Materials (BOM) and Master Production Schedule (MPS) for a
ID: 2496773 • Letter: B
Question
Below is the Bill of Materials (BOM) and Master Production Schedule (MPS) for a chair. The number in the parenthesis indicates the quantity needed and the lead time is shown in weeks.
Week
1
2
3
4
5
6
7
8
Quantity Needed
0
0
0
45
65
75
90
85
Determine the timing of the Planned Receipts and Planned Order Releases for the chairs assuming Scheduled receipts of 25 units in week 2 and 40 units in week 4 and a Projected On-hand Inventory of 20 units. Assume a L4L lot sizing rule with a lead time period of 2 weeks.
Item: Chairs Lot Size: L4L
Description: Lead Time: 2 week
Week
1
2
3
4
5
6
7
8
Gross
Requirements
Scheduled
Receipts
Projected
Available Balance
Net
Requirements
Planned
Receipts
Planned Order
Releases
Determine the timing of the Planned Receipts and Planned Order Releases for the leg assemblies assuming Scheduled receipts of 35 units in week 1 and a Projected On-hand Inventory on 40 units. Assume an Economic Order Quantity lot sizing rule where the EOQ is 100.
Item: Leg Assembly Lot Size: EOQ = 100
Description: Lead Time: 2 week
Week
1
2
3
4
5
6
7
8
Gross
Requirements
Scheduled
Receipts
Projected
Available Balance
Net
Requirements
Planned
Receipts
Planned Order
Releases
Week
1
2
3
4
5
6
7
8
Quantity Needed
0
0
0
45
65
75
90
85
Explanation / Answer
Item: Chairs Lot Size: L4L
Description: Lead Time: 2 Week
Week
1
2
3
4
5
6
7
8
Gross Requirements
45
65
75
90
85
Scheduled Receipts
25
40
Projected Available balance(20)
20
45
45
40
0
0
0
0
Net Requirements
Planned receipts
25
75
90
85
Planned Order releases
25
75
90
85
Item: Chairs Lot Size: L4L
Description: Lead Time: 2 Week
Week
1
2
3
4
5
6
7
8
Gross Requirements
45
65
75
90
85
Scheduled Receipts
25
40
Projected Available balance(20)
20
45
45
40
0
0
0
0
Net Requirements
Planned receipts
25
75
90
85
Planned Order releases
25
75
90
85
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.