Problem 2 Maksy Manufacturing uses a standard cost accounting system and produce
ID: 2496857 • Letter: P
Question
Problem 2
Maksy Manufacturing uses a standard cost accounting system and produced 32,000 units this past year. Each unit took several pounds of direct materials and 1.25 standard hours of direct labor at a standard hourly rate of $ 12.00. Budgeted activity was 50,000 direct labor hours. During the year, 133,000 pounds of raw materials were purchased at $0.92 per pound and used in the production. (Hint: Set up the 3-column format to compute variances; input the numbers given and back into the unknown amounts. Have fun!)
a. If the direct materials cost variance was $ 3,990 favorable, what was the standard materials cost per pound?
b. If the direct materials efficiency variance was $ 1,710 unfavorable, what was the standard materials quantity per unit?
c. What were the standard hours allowed for the units produced?
d. If the direct labor efficiency variance was $ 7,200 unfavorable, what were the actual direct labor hours worked?
e. If the direct labor cost variance was $ 6,090 favorable, what was the actual rate per hour?
Explanation / Answer
(a)
Direct material cost variance
= Standard cost x Actual quantity - Actual cost
So, $ 3,990 = Standard cost x 133,000 - 133,000 x $ 0.92
So, $ 3,990 + $ 122,360 = Standard cost x 133,000
So, Standard Cost = $ 126,350/133,000
= $ 0.95 per unit
(b)
Direct material efficiency variance
= Actual Quantity x Standard Price - Standard Quantity x Standard Price
So, $ 1,710 = 133,000 x $ 0.95 - Standard Quantity x $ 0.95
So, Standard Quantity x $ 0.95 = $ 124,640
So, Standard Quantity = $ 124,640/ $ 0.95
= 131,200 units
(c)
Standard hours allowed for units produced
= Standard hours per unit x Number of units produced
= 1.25 x 32,000 units
= 40,000 hours
(d)
Direct labor efficiency variance
= Actual Hours x Standard Rate - Standard Hours x Standard Rate
=So, $ 7,200 = Actual hours x $ 12 - 40,000 x $ 12
So, Actual hours = 40,600 hours
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.