Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Kerrybub Ltd. began building a new plant on 12/31/13. They paid $250,000 for ass

ID: 2497685 • Letter: K

Question

Kerrybub Ltd. began building a new plant on 12/31/13. They paid $250,000 for associated pre-construction costs (permits, architect, etc.) on that date also. Payments to the contractor occurred as follows:

Date

Amount in $

3/1/14

240,000

5/1/14

330,000

7/1/14

60,000

The plant was completed on 7/1/14.

To help finance construction of this plant Kerrybub borrowed $100,000 on 12/31/13 at 7%. In addition, Kerrybub had the following debt outstanding during 2014:

Principal

Rate

Due date

$300,000

6%

12/31/16

$300,000

5%

4/30/15

What is the total capitalized cost of this new plant?

Date

Amount in $

3/1/14

240,000

5/1/14

330,000

7/1/14

60,000

Explanation / Answer

Weighted average accumulated expenditure

Avoidable interest

specific debt     100,000 @7% *1/2              = $3,500

General debt     300,000 @6% *1/2             =   9,000

                          300,000 @5%*1/2               =   7,500

total                                                             = $20,000

Weighted average interest rate on general debt = 16,500/600,000 = 2.75%

hence capitalised cost will be $15,050

Date Amount Capitalisation period weighted average accumulated expenditure 12/31/13 $250,000 6/6 250,000 3/1/14 240,000 4/6 160,000 5/1/14 330,000 2/6 110,000 7/1/14 60,000 0/6            0 $520,000