Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Toan Inc. uses a job-order costing system in which any underapplied or overappli

ID: 2502975 • Letter: T

Question

Toan Inc. uses a job-order costing system in which any underapplied or overapplied overhead is closed to cost of goods sold at the end of the month. In September the company completed job S80M that consisted of 23,000 units of one of the company's standard products. No other jobs were in process during the month. The job cost sheet for job S80M shows the following costs:<?xml:namespace prefix = o ns = "urn:schemas-microsoft-com:office:office" />

During the month, the actual manufacturing overhead cost incurred was $270,020 and 3,000 completed units from job S80M were sold. No other products were sold during the month.
The unit product cost for job S80M is closest to:

a. $31.30

b. $43.00

c. $329.97

d. $329.67

Explanation / Answer

c. $329.97


is answer

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote