The Worldwide Credit Card, Inc., uses standards to control the labor time involv

ID: 2504818 • Letter: T

Question

The Worldwide Credit Card, Inc., uses standards to control the labor time involved in opening mail from card holders and recording the enclosed remittances. Incoming mail is gathered into batches, and a standard time is set for opening and recording each batch. The labor standards relating to one batch are as follows:

Standard Hours  

Standard Rate  

Standard Cost  

  Per batch

2.60        

$4.00        

$10.40       

The record showing the time spent last week in opening batches of mail has been misplaced. However, the batch supervisor recalls that 180 batches were received and opened during the week, and the controller recalls the following variance data relating to these batches:

  Total labor spending variance

$

578

U

  Labor rate variance

$

490

U

Required:

1.

Determine the number of actual labor-hours spent opening batches during the week.

  Actual labor hours

hours

2.

Determine the actual hourly rate paid to employees for opening batches last week. (Round your answer to 2 decimal places. Omit the "$" sign in your response.)

  Actual hourly rate

$

per hour

The Worldwide Credit Card, Inc., uses standards to control the labor time involved in opening mail from card holders and recording the enclosed remittances. Incoming mail is gathered into batches, and a standard time is set for opening and recording each batch. The labor standards relating to one batch are as follows:

Explanation / Answer

Labor Rate Variance = $ 490

Labor Efficiency Vriance = Total labor spending variance - Labor Rate Variance= (578-490) U = $ 88

DL Efficiency Variance = ( AH ? SH )