1. A firm is considering 2 options: A B First cost 10.7K 5.5K Annual benefits 2.
ID: 2507476 • Letter: 1
Question
1. A firm is considering 2 options:
A B
First cost 10.7K 5.5K
Annual benefits 2.1K 1.8K
Salvage 0 0
Useful life (yrs) 8 4
At what interest rate (integer) is option A = option B?
2. Three projects are being considered:
A B C
First cost 1,000 2,000 3,000
Annual benefits 150 150 0
Salvage 1,000 2,700 5,600
Life in years 5 6 7
When each life is reached, the machines will be salvaged, with no replacement.
At 8%, which project should be chosen?
Explanation / Answer
1
Let the rate be 'i'.
We need both the NPV to be same.
-10700 + 2100*PVA(i%,8) = -5500 + 1800*PVA(i%,4)
2100*PVA(i%,8) - 1800*PVA(i%,4) = -5500 + 10700
2100*PVA(i%,8) - 1800*PVA(i%,4) = 5200
On solving we get i=11%
Thus, at 11%, bith the projects are same.
2
NPV(A) = -1000 + 150*PVA(8%,5) + 1000*PV(8%,5)
= 279.53
NPV(B) = -2000 + 150*PVA(8%,6) + 2700*PV(8%,6)
= 394.91
NPV(C) = -3000 + 0*PVA(8%,7) + 1000*PV(8%,7)
= 267.55
Thus, we should select Project B
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.