Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

X Company uses an activity-based costing overhead allocation system. It has iden

ID: 2507927 • Letter: X

Question

X Company uses an activity-based costing overhead allocation system. It has identified three activities - Setup, Product Testing, Machine Maintenance - and their respective cost drivers - setup hours, tests, machine hours. Budgeted activity costs are as follows:

The following cost driver information is available for its products:

How much overhead was allocated to Product A (round overhead rates to the nearest cent)?

Activity Budgeted Cost   Setup $109,000       Product Testing 56,000       Machine Maintenance 56,000      

Explanation / Answer

Hi,


Please find the answer as follows:


Setup Cost Allocated to Product A = Total Budgeted Cost*Proportion of Set Up Hours for Product A/Total Hours = 109000*27000/806500 = 3649.10

+

Product Testing Cost Allocated to Product A = Total Budgeted Cost*Proportion of Tests for Product A/Tests for All Products = 56000*48400/917000 = 2955.73

+

Machine Maintenance Cost Allocated to Product A = Total Budgeted Cost*Proportion of Machine Hours for Product A/Machine Hours for All Products = 56000*75700/889200 = 4767.43


Overhead Cost Allocated to Product A = 3649.10 + 2955.73 + 4767.43 = 11372.26 or 11372


Answer is 11372.26 or 11372.


Thanks.