Stiner Builders contracted to build a high-rise for $14,000,000. Construction be
ID: 2508691 • Letter: S
Question
Stiner Builders contracted to build a high-rise for $14,000,000. Construction began in 2012 and is expected to be completed in 2015. Data for 2012 and 2013 are:
2012 2013
Costs incurred to date $1,800,000 $5,200,000
Estimated costs to complete 7,200,000 4,800,000
Stiner uses the percentage-of-completion method.
Instructions
25) How much gross profit should be reported for 2012? Show your computation.
Explanation / Answer
Calculate gross profit for 2012 :
2012 Cost incurrent to date 1800000 Estimated cost to completed 7200000 Total cost of contract 9000000 Percentage completion (1800000*100/9000000) 20% Contract revenue recognized in 2012 (14000000*20%) 2800000 Cost incurred recognized in 2012 (1800000) Gross profit recognized in 2012 1000000Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.