View History Bookmarks People Tue 9:26 PM Alexis Alonso Do Homework- Alexis Alonso Secure hnttps./www.mathal.com/Student PlayerHomework.aspxhomeworkld-46784630 ACG 2071 VIRTUAL COLLEGE 1&questionld-2;&flushed; faise&cid; 48 Alexis Alonso&1 4/3/18 926 PM Homework: Chapter 6 Homework Score: 0.15 of 1 pt 2 of 5 2complete) Score: 23.08%, 1.15 of 5 pts & E3-21A (similar to) E Question Help signage from eoycled plastics (primariy shredsed mk jugs.) Many of bhe company's ouastomers are s and necovered matera's.) As a resut, Lancaster includes two types of direct material charges in is joo cost for each joo: (1)wirg Lancaster Plastics manufactures oustom park furniture and municipalities that are nequired by law to purchase goods thait meet certain recycled-content guideines (jRecycled-content can include posd-consumer waste materas materials (non-recycled) and (2) recycled-content materials EB(Click the loon to view the additional data.) Read the nequirements ng he Requirement 1. Calcuae te total coat of the Nontion County ob Norton County Job Total job cost Choose from any list or enter any number in the input felds and then click Check Answer Clear Al Check Anewer

Explanation / Answer

Requirement – 1;

Virgin materials (200 pounds * $3.90)

$780

Recycled-content materials (200 pounds * $3.00)

$600

Direct labor (14 * $17)

$238

Manufacturing overhead (14 * $8)

$112

Total cost of the Norton Country Job

$1730

Requirement – 2;

Virgin materials used in Norton Country Job = 200 pounds

Recycled-content used in Norton Country Job = 200 pounds

So total materials used (200 + 200) = 400 pounds

Percentage of Recycled-content used in Norton Country Job (200 / 400) = 50%

This job does not meet requirements because actual used recycled-content is 50% whereas atleast 60% recycled-content to be used.

Virgin materials (200 pounds * $3.90)

$780

Recycled-content materials (200 pounds * $3.00)

$600

Direct labor (14 * $17)

$238

Manufacturing overhead (14 * $8)

$112

Total cost of the Norton Country Job

$1730