Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The followng informaion apples to the questions displayed below) Preble Compeny

ID: 2511210 • Letter: T

Question

The followng informaion apples to the questions displayed below) Preble Compeny manufactures one product ts variable manufacturing overhead is appled to production based on direct lebor hours and ts standard cost card per unit is s folows Direct meterisis 5 pounds et 38 per pound Direct leber 4 hours et $15 per hour Veriable overheed 4 hours et $5 per hour Totnl stendard cost per unit s 40 60 20 s 120 The planning budget for March was based on producing and selling 21,000 unts However during March the compeny actualy produced and soid 24,000 units and incurred the following conts a Purchased 150.000 pounds of rew matenials o cost of $6.40 per pound A of b. Direct laborers worked 66,000 hours at e rate of $18 per hour materai wos used in production ? tal variable nonfacturrgove head for te moth was $40820

Explanation / Answer

Solution:

Flexible budget is the budget prepared at standard cost but by taking the actual activity level achieved. It helps management to see the performance and compare the budgeted cost/revenue with the actual results.

8) Direct labor cost (flexible budget for March) = Actual Production 21,000 Units x Std Hours needed per unit 4 hours at $15 per hour

= $1,260,000

9)

Labor Rate Variance

Labor Price Variance – It arises due to difference in actual rate paid from standard rate. It is calculated as below:

Labor Price Variance = Actual Time (Standard Rate per hour – Actual Rate per hour)

Here, actual time means time for which wage has been paid.

Labor Rate Variance

Actual Hourly Rate (AHR)

$18.00

Per Hour

Standard Hourly Rate (SHR)

$15.00

Per Hour

Variance or Difference in Rate

$3.00

Per Hour

x Actual Labor Hours worked

66000

Hours

Labor Rate Variance

$198,000

Unfavorable

10)

Labor Quantity/Effieincy Variance

Labor Efficiency Variance – It arises due to variation in the working hours from the set standard.

Labor Quantity / Efficiency Variance

Standard Hours Allowed for actual production:

Actual Production

21000

Units

x Allowed Standard Hours Per Unit

4

hours

Total Standard Hours Allowed for actual production (SHAP)

84000

hours

Actual Labor Hours Worked (AH)

66000

hours

Variance or Difference in Hours

18000

hours

x Standard Hourly Rate (SHR)

$15.00

per hour

Labor Efficiency Variance

$270,000

Favorable

11) Labor Spending Variance = Labor Rate Variance $198,000 U + Labor Efficiency Variance $270,000 F

= $72,000 Favorable

Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you

Labor Rate Variance

Actual Hourly Rate (AHR)

$18.00

Per Hour

Standard Hourly Rate (SHR)

$15.00

Per Hour

Variance or Difference in Rate

$3.00

Per Hour

x Actual Labor Hours worked

66000

Hours

Labor Rate Variance

$198,000

Unfavorable

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote