Rey Custom Electronics (RCE) sells and installs complete security, computer, audio, and video systems for homes. On newly constructed homes it provides bids using time-and-material pricing. The following budgeted cost data are available.


The company has budgeted for 5,000 hours of technician time during the coming year. It desires a $ 37.00 profit margin per hour of labor and an 80% profit on parts. It estimates the total invoice cost of parts and materials in 2017 will be $ 650,000 .

RCE has just received a request for a bid from Buil Builders on a $ 1,150,000 new home. The company estimates that it would require 75 hours of labor and $ 35,000 of parts. Compute the total estimated bill. (Round answer to 2 decimal places, e.g. 10.50.)

   Time
Charges Material
Loading
Charges     Technicians' wages and benefits $ 100,000 -        Parts manager's salary and benefits -        $ 33,000 Office employee's salary and benefits 20,000 6,000 Other overhead 10,000 35,750 Total budgeted costs $ 130,000 $ 74,750

Explanation / Answer

Rate charged per labor hour 130,000/5000 +37 63 material load percentage 74750/650000+80% 91.5 % total estimated bill labor charges (75*63)= 4725 parts 35,000 material loading charges(35000*91.5%)= 32025 total estimated bill 71750 answer