Question
he following information applies to the questions displayed below.]
Assume that the company computes variances at the earliest point in time. The direct-labor efficiency variance is:
Assume that the company computes variances at the earliest point in time. The standard hours allowed for the work performed are:
Cost standards for one unit of product no. C77: Direct material 3 pounds at $2.80 per pound $8.40 Direct labor 6 hours at $7.40 per hour 44.40 Actual results: Units produced 6,600 units Direct material purchased 26,200 pounds at $3.00 $78,600 Direct material used 19,500 pounds at $3.00 58,500 Direct labor 40,700 hours at $7.20 293,040Explanation / Answer
Direct-labor efficiency variance = SR[AH-SH]
= 7.4 [40700 -(6600 * 6)]
7.4 [40700- 39600]
8140 U
standard hours allowed for the work performed =Actual units *Standard hours per unit
= 6600 * 6
= 39600 hours