The production manager of Rordan Corporation has submitted the following quarter
ID: 2520202 • Letter: T
Question
The production manager of Rordan Corporation has submitted the following quarterly production forecast for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 9,200 7,000 7,600 9,500 Each unit requires 0.35 direct labor-hours, and direct laborers are paid $10.00 per hour. Required: 1. Prepare the company’s direct labor budget for the upcoming fiscal year. Assume that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced. 2. Prepare the company’s direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is not adjusted each quarter. Instead, assume that the company’s direct labor workforce consists of permanent employees who are guaranteed to be paid for at least 3,000 hours of work each quarter. If the number of required direct labor-hours is less than this number, the workers are paid for 3,000 hours anyway. Any hours worked in excess of 3,000 hours in a quarter are paid at the rate of 1.5 times the normal hourly rate for direct labor.
Explanation / Answer
Required: 1. Prepare the company’s direct labor budget for the upcoming fiscal year. Assume that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced
2. Prepare the company’s direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is not adjusted each quarter. Instead, assume that the company’s direct labor workforce consists of permanent employees who are guaranteed to be paid for at least 3,000 hours of work each quarter. If the number of required direct labor-hours is less than this number, the workers are paid for 3,000 hours anyway. Any hours worked in excess of 3,000 hours in a quarter are paid at the rate of 1.5 times the normal hourly rate for direct labor.
1st quarter 2nd quarter 3rd quarter 4th quarter Year Production units 9200 7000 7600 9500 33300 Labour hour per unit 0.35 0.35 0.35 0.35 0.35 Labour hour for production 3220 2450 2660 3325 11655 Rate per hour 10 10 10 10 10 Direct labour cost 32200 24500 26600 33250 116550Related Questions