Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

tpx0.9596258696260781 1523818732096 Marvel Parts, Inc., manufactures auto access

ID: 2521949 • Letter: T

Question

tpx0.9596258696260781 1523818732096 Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearty any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,070 hours each month to produce 2,140 sets of covers. The standard costs associated with this level of production are Total of Covers Direct materials Direct labor Variable manufacturing overhead $26,964 $12.60 $ 11,770 5.50 $ 3,6381.70 $19.80 (based on direct labor-hours) During August, the factory worked only 1,000 direct labor-hours and produced 2,400 sets of covers. The following actual costs were recorded during the month Per Set Totalot Covers Direct materials (6,000 yards) Direct labor Variable manufacturing overhead $29.280 $12.20 $13,6805.70 S 5,7602.40 $20.30 At standard, each set of covers should require 1.50 yards of material All of the materials purchased during the month were used in production. Required: 1. Compute the materials price and quantity variances for August (Input all amounts as positive values Indicate the effect of each variance by selecting "F for favorable, "u" for unfavorable, and None" tor no effect (I.e, zero variance).) Materiats price variance Materals quanbty vaniance

Explanation / Answer

Materials price variance

Standard material price should have been

(26964 x 2400 /2140)

30240

Actual material price

29280

Materials price variance (30240 -29280)

960

F

Material quantity variance

Standard material quantity for 2400 sets of covers (2400 x 1.5)

3360

Actual quantity of material

6000

Material quantity variance (3360 - 6000)

-2640

U

Labour rate variance

Standard labour rate

5.5

Actual labour rate

5.7

Labour rate variance

{(5.5-5.7) x 100/5.5)}

-3.64

U

Labour efficiency variance

Standard number of hours required for production of 2140 sets

(11770 / 5.5)

2140

Thus, standard hours required for production 2400 covers

(2140 x 2400/2140)

2400

Actual hours needed to manufacture 2400 sets

(13680 / 5.7)

2400

Labour efficiency variance (2400-2400): No variance

Variable overhead rate variance

Standard variable overhead rate

1.7

Actual variable overhead rate

2.4

Variance (1.7-2.4)

-0.7

Variable overhead rate variance

(-0.7 x 100/1.7)

-41.1764706

Variable overhead efficiency variance (2400 2400) Note 1:

No variance

Note 1: Since the standard hours and actual hours are equal, 2400 hours hence, no variable overhead efficiency variance.

Materials price variance

Standard material price should have been

(26964 x 2400 /2140)

30240

Actual material price

29280

Materials price variance (30240 -29280)

960

F

Material quantity variance

Standard material quantity for 2400 sets of covers (2400 x 1.5)

3360

Actual quantity of material

6000

Material quantity variance (3360 - 6000)

-2640

U

Labour rate variance

Standard labour rate

5.5

Actual labour rate

5.7

Labour rate variance

{(5.5-5.7) x 100/5.5)}

-3.64

U

Labour efficiency variance

Standard number of hours required for production of 2140 sets

(11770 / 5.5)

2140

Thus, standard hours required for production 2400 covers

(2140 x 2400/2140)

2400

Actual hours needed to manufacture 2400 sets

(13680 / 5.7)

2400

Labour efficiency variance (2400-2400): No variance

Variable overhead rate variance

Standard variable overhead rate

1.7

Actual variable overhead rate

2.4

Variance (1.7-2.4)

-0.7

Variable overhead rate variance

(-0.7 x 100/1.7)

-41.1764706

Variable overhead efficiency variance (2400 2400) Note 1:

No variance