Question
WileyPLUS e I https//edugen.wileyplus.com/edugen/student/mainfr.uni US Kimmel, Accounting, 6e PRINCIPLES OF ACCOUNTING (ACE 211 and 212 ractice Gradebook ORION Downloadable eTextbook Multiple Choice Question 86 Sunland Company produced 270000 units in 125000 direct labor hours. Production for the period was estimated at 2180000 units and 140000 direct labar e budget would compare budgeted costs and actual costs, respectivety 0 135000 hours and 125000 hours. O 140000 hours and 125000 hours. 125000 hours and 12500 hours. 135000 hours and 140000 hours. Question Attempts: 0 of 1 used sAVE FOR LATesExplanation / Answer
Actual unit produced = 270000 units
Actual hour = 125000 hour
Flexible budget hour = (140000/280000)*270000 = 135000
so answer is a) 135000 hours and 125000 hours
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.