Do It! Review 22-3 Presented below are data relating to labor for Verde Appliance Repair Shop. Repair-technicians' wages Fringe benefits Overhead $142,184 41,104 62,216 The desired profit margin per hour is $20.55. The material loading charge is 60% of invoice cost. Verde estimates that 5,600 labor hours will be worked next year. If Verde repairs a dishwasher that takes 1.6 hours to repair and uses parts of $81.50, compute the bill for the job. (Round answer to 2 decimal places, e.g. 10.50.) Total cost LINK TO TEXT

Explanation / Answer

Solution: Total cost : 233.42

Working:

Repair-technicians’ wages

142,184

5,600

25.39

Fringe benefits

41,104

5,600

7.34

Overhead

62,216

5,600

11.11

245,504

43.84

Profit margin

20.55

Rate charged per hour of labor

64.39

Material cost

81.50

Material loading charges (81.5*60%)

48.90

Total material cost

130.40

Cost of dishwasher repair

Labor costs (64.39 * 1.6)

103.02

Material cost

130.40

Total repair cost

233.42

Repair-technicians’ wages

142,184

5,600

25.39

Fringe benefits

41,104

5,600

7.34

Overhead

62,216

5,600

11.11

245,504

43.84

Profit margin

20.55

Rate charged per hour of labor

64.39

Material cost

81.50

Material loading charges (81.5*60%)

48.90

Total material cost

130.40

Cost of dishwasher repair

Labor costs (64.39 * 1.6)

103.02

Material cost

130.40

Total repair cost

233.42