Direct Labor Variances
La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available:
a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
b. How much direct labor should be debited to Work in Process?
$
Explanation / Answer
Ans: a.
1. Direct labor rate variance= (Actual labor rate per hour-standard rate per hour)*quantity of direct labor used
= ($13.4-$13.7)*550=-$165 “Favorable”
2. Direct Labor time variance
= ( quantity of direct labor actually used- standard direct labor allowed for 260 bicycles)*standard labor rate per hour
= (550-260*2)*$13.7
= $411”Unfaborable”
3. Total direct labor cost variance= Direct labor rate variance+ Direct labor time variance
= -$165+$411
= $246 “unfavorable”
b. Direct labor debited to work in process= standard direct labor allowed*standard labor rate per hour
= 520*$13.7=$7124