Review the attached file Associated with this question which contains a PERT diagram. What is the critical path completion time (number of weeks) for this project? Please enter the number only...no other text or characters.
Review the attached file Associated with this question which contains a PERT diagram. What is the critical path completion time (number of weeks) for this project? Please enter the number only...no other text or characters.
Install computer Parallel run of Test computer revisions to Revise & update T- 2 (T-2) Modify existing Test existing Implement new (T- 3) (T-4) T- 2 (T-2) Design new Evaluate manpowerT- 2) Test new applications Revise new T- 3) (T- 3) T-2) Hire additional Program new Second test of new application (T- 2) (T- 6) L. (T-2)Explanation / Answer
Critical path is the path that takes the maximum amount of time to complete a particular project or work. Accordingly, the following path takes the maximum amount of time to complete the project in this case.
A>E = 8
E>F = 6
F>I = 2
I>J = 2
J>N = 2
N>P = 2
Thus, critical path competition time is (8+6+2+2+2+2) = 22 weeks.