An employee of A/C Corporation has found some partially completed units of Model
ID: 2537357 • Letter: A
Question
An employee of A/C Corporation has found some partially completed units of Model X in a dusty corner of the warehouse. A job ticket attached to the units indicates that a total of $850 in manufacturing costs have been used to bring the materials to this point in the manufacturing process. The units can be sold in their current condition for $275 to a scrap metal dealer. If A/C Corporation spends $285 to complete the units, they could be sold for $600.
(a) What should A/C Corporation do? Why?
(b) Identify the sunk cost, if any.
Explanation / Answer
Income if scrapped = 275
Income if work is done and sold at higher price = 600 - 285 = 315
Since the net income is higher in the second alternative, A/c Corporation should rework on the scrap and sell it at a higher price
Sunk costs are costs that have already been incurred and are not considered relevant for decision making
In the above example the original cost of 850 is a sunk cost