Question

Blac Exam B 2018 Online ACCT 2302.90L instructions help Question 20 (of 25 Save & Exit Submit Time remaining: 1.28:46 Sherman, Inc. manufactures chainsaws that sell for $250. Each chainsaw uses $12 in direct materials and $7 in direct labor per unit. Sherman has two activities which is applied at the rate of $5 per machine hour, and Finishing which is applied at the rate of $23 per batch. This month, Sherman mede 250 chainsews, using 8 machine hours in 40 batches. What is the total m Machining 16 anufecturing cost for one chainsew? (Do not round intermediate calculations,) O $42 O $20 O $19 O $39 Type here to search

Explanation / Answer

Direct material : 12

Direct labour. :. 7

Machining cost .: 16.32 (816/250*5)

Finishing cost :. 3.68 (40/250*23)

Total cost per chainsaw : 39