Bienestar, Inc., has done a cost analysis for its production of vests. The follo
ID: 2554864 • Letter: B
Question
Bienestar, Inc., has done a cost analysis for its production of vests. The following activities and cost drivers have been developed:
Following are the actual costs of producing 75,000 vests: 5,000 machine hours; 10 batches; 20 purchase orders
What is the budget variance for setups in an activity-based performance report?
Explanation / Answer
$2,000 F
The budget variance for setups in an activity-based performance report is $2,000 F.
Actual $18,000 Budget($2,000 * 10) $20,000 Variance $2,000 FRelated Questions