direct labour hours During the yea and two of direst materials purchased eere ua
ID: 2555936 • Letter: D
Question
direct labour hours During the yea and two of direst materials purchased eere uaed during the yess 200.000 kg of sials were puchd (a) If the ws s10.000 unfavourable, What were the standard (d) If the labour (e) If the labour pricarce (D If total budgeted what was the standard materials price per kilogrm tavourable, whas was the standard materials quantity per was $18.168 favourable, what was the actual rate per hour actual direct labour hours worked per direct labour hours? g) What was the standard cost per unit of productt (b) How much overhead was applied to production during the year? a) Using one or more answers above, what were the total costs assigned to work in overhead was $713,800 at normal capacity, what was the p acturing Company uses a standard cost system cost system in accounting for the cost of one of its products. on is 1,750 units per month. The standard direct labour cost is 15 hours per unit at ss pet 1So 2.3) The budgeted hour. The budgeted cost for manufa monthly p accounting ucti g overhead is set as follows: Fixed overhead per month Variable overhead per month Total budgeted overhead 5183,750 78,750 The manufacturing overhead rate is 200% of the direct labor cost. During the month of April, the plant produced 1,650 units and the cost of production was as follows: Direct materials (99,000 litres) Direct labour (23,100 hours) Fixed manufacturing overhead Variable manufacturing overhead s792.000 121,275 195,000 63,525 $1,171,800 Instructions Calculate the following: (a) Labour price and quantity variances (b) Variable overhead spending and quantity variances (c) Fixed overhead spending and volume variances (b) LQV (adapted from CPA Canada)Explanation / Answer
Solution:
Part a – Labor Rate and Quantity Variance
Labor Rate Variance
Labor Price Variance – It arises due to difference in actual rate paid from standard rate. It is calculated as below:
Labor Price Variance = Actual Time (Standard Rate per hour – Actual Rate per hour)
Here, actual time means time for which wage has been paid.
Labor Rate Variance
Actual Hourly Rate (AHR) ($121,275 / 23,100 hrs)
$5.25
Per Hour
Standard Hourly Rate (SHR)
$5.00
Per Hour
Variance or Difference in Rate
$0.25
Per Hour
x Actual Labor Hours worked
23100
Hours
Labor Rate Variance
$5,775
Unfavorable
Unfavorable Labor Rate Variance because actual hourly rate paid is higher than standard hourly rate.
Labor Quantity Variance
Labor Efficiency Variance – It arises due to variation in the working hours from the set standard.
Labor Quantity / Efficiency Variance
Standard Hours Allowed for actual production:
Actual Production
1650
Units
x Allowed Standard Hours Per Unit
15
hours
Total Standard Hours Allowed for actual production (SHAP)
24750
hours
Actual Labor Hours Worked (AH)
23100
hours
Variance or Difference in Hours (SHAP - AH)
1650
hours
x Standard Hourly Rate (SHR)
$5
per hour
Labor Efficiency Variance
$8,250
Favorable
Labor Efficiency Variance is Favorable because the Actual Hours Worked is lesser than the allowed standard hours.
Part b --- Variable Overhead Spending and Quantity Variance
Variable Overhead Spending/Rate Variance
Actual Hourly Variable Overhead Rate
($63,525 / 23,100 actual hours)
2.75
Per Hour
Standard Hourly Variable Overhead Rate (SV) (Refer Note 1)
3.00
Per Hour
Variance or Difference in Rate
0.25
Per Hour
x Actual Direct Labor Hours Worked
23100
Hours
Variable Overhead Rate Variance
$5,775
Favorable
Favorable because Actual Variable Overhead is less than anticipated
Note 1 – Standard Hourly Variable Overhead Rate = Total Budgeted Variable Overhead Cost / Total Budgeted Direct Labor Hours
= $78,750 / (1750Units*15 hrs per unit)
= 78,750 / 26,250
= $3 per hour
Variable Overhead Efficiency/Quantity Variance
Standard Hours Allowed for actual production:
Actual Production
1,650
Units
x Allowed Standard Hours Per Unit
15
hours
Total Standard Hours Allowed for actual production (SHAP)
24750
hours
Actual Direct Labor Hours (AH)
23100
Hours
Variance or Difference in Hours (SHAP - AH)
1650
hours
x Standard Hourly Variable Overhead Rate (Refer Note 1)
$3.00
per hour
Variable Overhead Efficiency Variance
$4,950
Favorable
Favorable because actual hours worked is less than anticipated
Part c --- Fixed Overhead Spending and Volume Variance
Fixed Overhead Expenditure/Spending Variance
Budgeted Fixed Overheads (BFOH)
$183,750
Actual Fixed Overheads (AFOH)
$195,000
Fixed Overhead Expenditure Variance (AFOH - BFOH)
$11,250
Unfavorable
Fixed Overhead Volume Variance
Absorbed Fixed Overheads (A)
(Actual Hours worked 23,100 x Standard fixed overhead rate per hour $7)
$161,700
Budgeted Fixed Overheads (B)
$183,750
Fixed Overhead Volume Variance (B -A)
$22,050
Unfavorable
Note --- Standard Fixed Overhead Rate per hour = Total Budgeted FOH / Total Budgeted Direct Labor Hour as calculated in part 1
= $183,750 / 26,250 hrs
= $7 per hour
Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you
Labor Rate Variance
Actual Hourly Rate (AHR) ($121,275 / 23,100 hrs)
$5.25
Per Hour
Standard Hourly Rate (SHR)
$5.00
Per Hour
Variance or Difference in Rate
$0.25
Per Hour
x Actual Labor Hours worked
23100
Hours
Labor Rate Variance
$5,775
Unfavorable
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.