Lupo Corporation uses a job-order costing system with a single plantwide predete
ID: 2558116 • Letter: L
Question
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost variable manufacturing overhead per machine- hour 30,000 $252,000 2.10 0007:36 Recently, Job T687 was completed with the following characteristics: Nunber of units in the job Total machine-hours Direct materials Direct labor cost 10 30 $ 675 $1,050 The estimated total manufacturing overhead is closest to: Multiple Choice 315,000 5252,000 5252,002 563,000Explanation / Answer
Estimated total manufacturing overhead = Variable manufacturing overhead+fixed manufacturing overhead
= (30000*2.10+252000)
Estimated total manufacturing overhead = 315000
so answer is a) $315000
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.