Direct Labor Variances
La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available:
a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
b. How much direct labor should be debited to Work in Process?
$
Explanation / Answer
a) Direct labor rate variance (actual rate - standard rate)*actual hours (14.1-14.4)*540 162 F time variance (actual hours - standard hours allowed)*standard rate (540 - 250*2)*14.4 576 U total direct labor cost variance 414 U b) Direct labor hour debited to work in process inventory 250*2*14.4 7200 answer
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.