Rhed Kennel uses tenant-days as its measure of activity; an animal housed in the
ID: 2564665 • Letter: R
Question
Rhed Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During December, the kennel budgeted for 3,800 tenant-days, but its actual level of activity was 3,750 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for December:
Data used in budgeting:
Actual results for December:
The activity variance for administrative expenses in December would be closest to:
Multiple Choice
$980 F
$20 U
$980 U
$20 F
Fixed element per month Variable element per tenant-day Revenue - $ 34.10 Wages and salaries $ 2,400 $ 7.90 Food and supplies 1,500 13.10 Facility expenses 8,400 4.60 Administrative expenses 6,400 0.40 Total expenses $ 18,700 $ 26.00Explanation / Answer
Activity Variance is the difference between planning and flexible budget.
Here Planning cost for administrative expense is 6,400 + (0.4*3,800) = 7,920
Flexible budget cost is 6,400 + (0.4*3,750) = 7,900
So activity variance is $20 F
Correct answer is D.