Exercise M-9 Rey Custom Electronics (RCE) sells and installs complete security, computer, audio, and video systems for homes. On newly constructed homes it provides bids using time-and material pricing. The following budgeted cost data are available Time Charges Material Loading Charges Technicians' wages and benefits $145,292 Parts manager's salary and benefits Office employee's salary and benefits 27,562 Other overhead Total budgeted costs $34,100 6,160 41,401 $188,417 81,661 15,563 The company has budgeted for 5,940 hours of technician time during the coming year. It desires a $38.88 profit margin per hour of labor and an 80% profit on parts. It estimates the total invoice cost of parts and materials in 2017 will be $671,000 Compute the rate charged per hour of labor. (Round answer to 2 decimal places, e.g. 10.50.) Labor rate s per hourExplanation / Answer
1)Labor rate per Hours = cost per hour +Profit margin
=[188417/5940]+38.88
= 31.72+38.88
= $ 70.60 per hour
2)Total cost per part :81661/671000 = .1217 or12.17%
Material load percentage : Total cost %+ margin%
= 12.17%+80%
= 92.17%
3)Total estimated bill :
Labor charges [70.6*80] 5648 Material charges Cost of parts 36700 Material loading % [.9217*36700] 33826.39 Total estimated bill 76174.39Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.