Montoursville Control Company, which manufactures electrical switches, uses a st
ID: 2572540 • Letter: M
Question
Montoursville Control Company, which manufactures electrical switches, uses a standard-costing system. The standard production overhead costs per switch are based on direct-labor hours and are as follows: Variable overhead (4 direct-labor hours$14.00 per hour) Fixed overhead (4 direct-labor hours $26.00 per hour) $ 56 104 Total overhead $160 Based on capacity of 310,000 direct-labor hours per month. The following information is available for the month of October. Variable overhead costs were $5,940,000 Fixed overhead costs were $8,625,000. 74,500 switches were produced, although 77,500 switches were scheduled to be produced. .295,000 direct-labor hours were worked at a total cost of $5,825,000 Required Compute the variable-overhead spending and efficiency variances and the fixed-overhead budget and volume variances for October. (Indicate the effect of each variance by selecting "Favorable" or "unfavorable". Select "None" and enter 0" for no effect zero variance).) Variable-overhead spending variance Variable-overhead efficiency variance Fixed-overhead budget variance Fixed-overhead volume varianceExplanation / Answer
Solution:
Variable Overhead Spending Variance
Actual Variable Overhead (A)
$5,940,000
Standard Variable Overhead (295,000 Hours x $14) (B)
$4,130,000
Variable Overhead Spending Variance (A-B)
$1,810,000
Unfavorable
Variable Overhead Efficiency Variance
Standard Hours Allowed for actual production:
Actual Production
74,500
Switches
x Allowed Standard Hours Per Unit
4
hours
Total Standard Hours Allowed for actual production (SHAP)
298000
hours
Actual Labor Hours Worked (AH)
295000
Hours
Variance or Difference in Quantity (SHAP - AH)
3000
hours
x Standard Hourly Variable Overhead Rate
$14
per hour
Variable Overhead Efficiency Variance
$42,000
Favorable
Fixed Overhead Budgeted Variance
Budgeted Fixed Overheads (BFOH)
(310,000 Budgeted DLHs x $26 per hour)
$8,060,000
Actual Fixed Overheads (AFOH)
$8,625,000
Fixed Overhead Expenditure Variance (BFOH - AFOH)
$565,000
Unfavorable
Fixed Overhead Volume Variance
Absorbed Fixed Overheads (A)
(Actual Direct labor hour worked 295,000 Hours x Budgeted Fixed Overhead Rate $26 per hour)
$7,670,000
Budgeted Fixed Overheads (B)
$8,060,000
Fixed Overhead Volume Variance (A-B)
$390,000
Unfavorable
Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you
Variable Overhead Spending Variance
Actual Variable Overhead (A)
$5,940,000
Standard Variable Overhead (295,000 Hours x $14) (B)
$4,130,000
Variable Overhead Spending Variance (A-B)
$1,810,000
Unfavorable
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.