Schlaefer Corporation is conducting a time-driven activity-based costing study in its Tech Support Department. The company has provided the following data to aid in that study: Schlaefer Corporation Tech Support Department Data Inputs Resource Data: Number of employees 16 Average salary per employee $ 46,440 Weeks of employment per year 50 Minutes available per week (40 hours × 60 minutes) 2,400 Practical capacity percentage 90 % Activity Data: Routing Calls Resolving Problems Preparing Change Orders Minutes per unit of the activity 16 26 32 Cost Object Data: All Customers Number of calls routed 43,740 Number of problems resolved 21,130 Number of change orders prepared 2,220 On the Capacity Analysis report in time-driven activity-based costing, the “unused capacity in minutes” would be closest to: 635,870 minutes 407,740 minutes 864,000 minutes 1,320,260 minutes

Explanation / Answer

Unused capacity in minutes would be closest to 407740 minutes

Weeks of employment per year 50 Minutes available per week 2400 Total minutes of employment per year 50*2400 120000 Number of employees 16 Total minutes available 120000*16 1920000 Practical Capacity 1920000*90% 1728000 Used Capacity: Routing calls Resolving problems change orders Number 43740 21130 2220 Minutes used 16 26 32 Total minutes used 699840 549380 71040 1320260 Available minutes 1728000 Unused capacity 407740
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote