Setting Standards, Material and Labor Variances Granite, per square foot $50.00
ID: 2577928 • Letter: S
Question
Setting Standards, Material and Labor Variances
Granite, per square foot
$50.00
Glue (10 oz. @ $0.15)
1.50
Direct labor hours:
Cutting labor (0.10 hr. @ $15)
1.50
Installation labor (0.25 hr. @ $25)
6.25
These standards assumed that one seamless counter requires one sink cut (the space into which the sink will fit) as well as cutting the counter to fit the space available.
Charlene tracked the actual costs incurred by Tom and Tony for granite installation for the next six months. She found that they completed 50 jobs with an average of 32 square feet of granite installed in each one. The following information on actual amounts used and cost was gathered:
Granite purchased and used (1,640 sq. ft.)
$80,248
Glue purchased and used (16,000 oz.)
$2,560
Actual hours cutting labor
180
Actual hours installation labor
430
The actual wage rate for cutting and installation labor remained unchanged from the standard rate.
Required:
If an amount is zero, enter "0" and select neither from the dropdown. If required, enter favorable values as negative numbers.
1. Calculate the materials price variances and materials usage variances for granite and for glue for the past six months.
Granite
Materials price variance ????
$
Favorable
Materials usage variance 2,000
$
Unfavorable
Glue
Materials price variance 160
$
Unfavorable
Materials usage variance 0
$
Neither
Granite, per square foot
$50.00
Glue (10 oz. @ $0.15)
1.50
Direct labor hours:
Cutting labor (0.10 hr. @ $15)
1.50
Installation labor (0.25 hr. @ $25)
6.25
Explanation / Answer
Step 1 - Preparing Flexible budget with actual Data for variance calculation
(A) Granite Material
1600 square feet
(50 jobs * 32 square feet)
Granite Material Variance
Formula = [Standard rate - Actual rate] * Actual quantity
Values : Standard rate = $50
Actual Rate = $48.93
Actual quantity = 1640 square feet
Values : Standard price = $50
Standard quantity = 1600 square feet
Actual quantity = 1640 square feet
(B) Glue material
Glue material variance
[(Standard rate - Actual rate)] * Actual oz
Values : Standard rate = $0.15
Actau rate = $0.16
Actual oz = 16000 oz
[Standard quantity - Actual quantity] * Standard rate
Value
Actual quantity = 16000 oz
Standard quantity = 16000 oz
Standard rate = $0.15
Particulars Flexible Data (revised standard data with respect to actual data) Actual budget Granite purchased and used1600 square feet
(50 jobs * 32 square feet)
1640 sqaure feet Total cost of granite purchase $80000 $80248 Cost per square feet of granite $50 $48.93Related Questions