38. Required information Assume that the company computes variances at the earli
ID: 2577958 • Letter: 3
Question
38.
Required information
Assume that the company computes variances at the earliest point in time. The direct-labor efficiency variance is:
$8,036F.
$8,036U.
$6,000F.
$6,000U.
None of these.
39.
Required information
Assume that the company computes variances at the earliest point in time. The standard hours allowed for the work performed are:
rev: 10_25_2011
40,280.
39,750.
39,600.
39,500.
None of these.
Cost standards for one unit of product no. C77: Direct material 3 pounds at $2.50 per pound $7.50 Direct labor 6 hours at $7.50 per hour 45.00 Actual results: Units produced 6,600 units Direct material purchased 25,900 pounds at $2.70 $69,930 Direct material used 19,500 pounds at $2.70 52,650 Direct labor 40,400 hours at $7.30 294,920Explanation / Answer
38) Direct labour efficiency variance = (Standard hours-actual hours)standard rate
= (6600*6-40400)7.50
Direct labour efficiency variance = 6000 U
so answer is d) 6000 U
39) Standard hours allowed for the work performed are = 6600*6 = 39600
so answer is c) 39600
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.