Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

E9-7 Calculating Direct Labor Variances LO 9-4) Parker Plastic, Inc., manufactur

ID: 2581024 • Letter: E

Question

E9-7 Calculating Direct Labor Variances LO 9-4) Parker Plastic, Inc., manufactures plastic mats to use with rolling office chairs. Its standard cost information for last year follows: Standard QuantityStandard Price (Rate) Standard Unit Cost 4.05 0.39 0.66 Direct materials (plastic) Direct labor Variable manufacturing overhead (based on S 11.70 9 sqft.1.30 per sq, ft. 0.3 hr 13.50 per hr 1.30 per hr 0.3 hr direct labor hours) Fixed manufacturing overhead $619,080 ÷ 938,000 units) Parker Plastic had the following actual results for the past year Number of units produced and sold Number of square feet of plastic used Cost of plastic purchased and used Number of labor hours worked Direct labor cost Variable overhead cost Fixed overhead cost 1,000,000 12,800,000 $ 15,360,000 336,000 S 4,200,000 $ 1,700,000 S 393,000 Required Calculate Parker Plastic's direct labor rate and efficiency variances. (Do not round intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable.) Direct Labor Rate Varance Direct Labor Efficiency Variance

Explanation / Answer

Solution:

Labor Rate/Price Variance

Labor Price Variance – It arises due to difference in actual rate paid from standard rate. It is calculated as below:

Labor Price Variance = Actual Time (Standard Rate per hour – Actual Rate per hour)

Here, actual time means time for which wage has been paid.

Labor Rate Variance

Actual Hourly Rate (AHR) (Actual labor cost $4,200,000 / Number of hour worked 336,000)

$12.50

Per Hour

Standard Hourly Rate (SHR)

$13.50

Per Hour

Variance or Difference in Rate

$1.00

Per Hour

x Actual Labor Hours worked

336000

Hours

Labor Rate Variance

$336,000

Favorable

Labor Efficiency / Usage Variance

Labor Efficiency Variance – It arises due to variation in the working hours from the set standard.

Labor Efficiency Variance = Standard Rate (Std. hours for actual production – Actual Hours)

Labor Efficiency Variance

Standard Hours Allowed for actual production:

Actual Production

1000000

Units

x Allowed Standard Hours Per Unit

0.3

hours

Total Standard Hours Allowed for actual production (SHAP)

300000

hours

Actual Labor Hours Worked (AH)

336000

hours

Variance or Difference in Quantity (AH - SHAP)

36000

hours

x Standard Hourly Rate (SHR)

$14

per hour

Labor Efficiency Variance

$486,000

Unfavorable

Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you

Labor Rate Variance

Actual Hourly Rate (AHR) (Actual labor cost $4,200,000 / Number of hour worked 336,000)

$12.50

Per Hour

Standard Hourly Rate (SHR)

$13.50

Per Hour

Variance or Difference in Rate

$1.00

Per Hour

x Actual Labor Hours worked

336000

Hours

Labor Rate Variance

$336,000

Favorable