Expected, Standard, and Actual Labor Hours
The Pizza Company makes two types of frozen pizzas: pepperoni and cheese. The Pizza Company allocates overhead to these two products based on the number of direct labor hours. The direct labor hours per unit for making a pepperoni pizza is 5 minutes or 1/12 of an hour. The direct labor hours per unit for making a cheese pizza is 4 minutes or 1/15 of an hour. At the start of the year the Pizza Company expected to make 12,000 pepperoni pizzas and 6,000 cheese pizzas. During the year, the Pizza Company actually made 9,000 pepperoni pizzas and 7,500 cheese pizzas. The time cards indicate that direct laborers worked for 1,300 hours. What are the total expected direct labor hours, standard direct labor hours, and actual direct labor hours?
Explanation / Answer
Expected Direct Labour Hours:-
Co.Expected 12000 Pepporoni pizza which reqd 12000/12=1000 Labour Hours
Co. Expected 6000 cheese pizza which required 6000/15=400 Labour Hours
Total expected Labour Hours =1000+400=1400Labour hours
Standard Labour Hours for making 9000 pepperoni pizzas=9000/12=750 hours
Standard Labour Hours for making 7500cheese pizzas
7500/15=500hours
Total standard Labour Hours=750+500=1250 hours
Actual direct Labour Hours taken from time card =1300hours