[The following information applies to the questions displayed below,] Most Compa
ID: 2586143 • Letter: #
Question
[The following information applies to the questions displayed below,] Most Company has an opportunity to invest in one of two new projects. Project Y requires a $335,000 investment for new machinery with a five-year life and no salvage value. Project Z requires a $335,000 investment for new machinery with a four-year life and no salvage value. The two projects yield the following predicted annual results. The company uses straight-line depreciation, and cash flows occur evenly throughout each year. (FV of $1, PV of $1, FVA of $1 and PVA of $1) (Use appropriate factor(s) from the tables provided.) Project Y Project Z $355,000 284,000 Sales Expenses Direct materials Direct labor Overhead including depreciation Selling and administrative expenses 49,700 71,000 127,800 25,000 35,500 42,600 127,800 25,000 Total expenses 273,500 230,900 Pretax income Income taxes (28%) 81,500 22,820 53,100 14,868 Net income $ 58,680 38,232 Required 1. Compute each project's annual expected net cash flows Project Y Project ZExplanation / Answer
Net income = revenue - all cash and non- cash expenses
But for get the 'Cash Flow' we need to add back the non-cash expenses to the net income (after tax).in this case it is depreciation.depreciation is a non-cash expense company does't have any cash outflow for the depreciation expense.so it should add back to the net income and also helps to get a tax reduction. Because of this feature depreciation also known as "Tax shield".
1)
PROJECT Y
Project's annual expected net cash flow = net income + depreciation
*)net income =58680
*)depreciation = 335000÷5 = 67000
Net cash flow = 58680+67000 = 125680 per year (for 5 years)
PROJECT Z
Annual expected net cash flow = Net income + depreciation
*)net income = 38232
*)depreciation = 335000 ÷ 4 = 83750
Net cash flow = 83750+38232 = 121982 per year. (for four years)
2)
Payback period = initial investment ÷ annual expected net cash flow
PROJECT Y
*)Annual expected net cash flow =125680
*)Initial investment = 335000
Payback period = 335000 ÷ 125680=2.66 or 2.66 years
PROJECT Z
*)initial investment = 335000
*)net cash flow = 121982
payback period = 335000 ÷ 121982 = 2.75
( from payback period analysis we can conclude that PROJECT Y is better than PROJECT Z because Y have small payback period.)
3)
PROJECT Y
Present value = 9% annuity factor for five years × annual cash flow
9% annuity factor = 3.88
annual cash flow =125680
present value = 3.88 × 125680 = 488895
*)Net present value (NPV) = present value of future cashflow - initial investment
present value of cashflow =487638
initial investment = 335000
NPV = 488895-335000 = 153895
PROJECT Z
Present value = 9% annuity factor for four years × net cash flow
9% annuity factor = 3.24
net cash flow =121982
present value =3.24 ×121982 =395222
NPV = Present value - initial investment
present value =395222
initial investment = 335000
NPV =395222-335000 = 60222
"Annuity factor rounded (Approx)"
(With respect to NPV results PROJECT Y is more favourable than PROJECT Z.)
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.