The master budget of Marigold Corp. shows that the planned activity level for ne
ID: 2586541 • Letter: T
Question
The master budget of Marigold Corp. shows that the planned activity level for next year is expected to be 50000 machine hours. At this level of activity, the following manufacturing overhead costs are expected:
Question 1 The master budget of Marigold Corp. shows that the planned activity level for next year is expected to be 50000 machine hours. At this level of activity, the following manufacturing overhead costs are expected: Indirect labor Machine supplies Indirect materials Depreciation on factory building Total manufacturing overhead$1370000 $800000 250000 250000 70000 A flexible budget for a level of activity of 60000 machine hours would show total manufacturing overhead costs of $1630000 O $1370000. $1644000. $1574000.Explanation / Answer
Total variable cost=(800,000+250,000+250,000)=$1,300,000
Hence VC/unit=(1,300,000/50,000)=$26
NHence total overhead cost at 60,000 hours=(60000*26)+70,000
=$1,630,000(A)
NOTE:Total fixed costs and variable cost/unit do not change with change in units.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.