Nash Corporation manufactures and sells custom snowmobiles. From the time an ord

ID: 2588705 • Letter: N

Question

Nash Corporation manufactures and sells custom snowmobiles. From the time an order is placed till the time the snowmobile reaches the customer averages 104 days. This 104 days is spent as follows:

What is Nash's manufacturing cycle efficiency (MCE) for its snowmobiles? (Round you answer to 1 decimal place.)

41.3%

58.7%

31.0%

56.7%

Nash Corporation manufactures and sells custom snowmobiles. From the time an order is placed till the time the snowmobile reaches the customer averages 104 days. This 104 days is spent as follows:

Explanation / Answer

manufacturing cycle efficiency=Process time/(Process time+Move time+Queue time+Inspection time)

=26/(17+26+25+16)

which is equal to

=31%(Approx)