newconnect mheducation.com YouTube . 2017/ (h ) cS·~ . Jen Gonnect MGR ACCT 2060 CH 11 HW EX 11-3 FALL 2017 Saved Help Save & Exit Submit Check my work Management of Mittel Rhein AG of Köln, Germany. would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported 10 points 0.5 days 16.6 days Inspection time Wait tine (from order to start of produetion) Process tine Move time Queue tine .4 days 1.3 days 3.5 days eBook Print Required: ound your (Roun your the throughput time. (Round your answer to 1 decimal place.) Peferences 2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent) 3. What percentage of the throughput time was spent in non-value-added activities? (Round your percentage answer to nearest whole percent.) 4. Compute the delivery cycle time. (Round your intermediate calculations and final answer to 1 decimal place) calculations. Round your percentage answer to nearest whole percent.) using Lean Production all queue time during production is eliminated, what will be the new MCE? (Do not round intermediate days 1.Throughput time 2. Manufacturing cycle efficiencyExplanation / Answer
Question 1). Solution :- Throughput time = Inspection time + Process time + Move time + Queue time.
= 0.5 + 3.4 + 1.3 + 3.5
= 8.7 Days.
Conclusion :- Throughput time = 8.7 Days.
Question 2). Solution :- Manufacturing cycle efficiency (MCE) = Process time / Throughput time.
= 3.4 Days / 8.7 Days
= 0.39 i.e., 39 %
Conclusion :- Manufacturing cycle efficiency (MCE) = 39 %
Question 3). Solution :- Percentage of throughput time spent in non-value added activities = 1 - 0.39
= 0.61 i.e., 61 %
Conclusion :- Percentage of throughput time spent in the non-value added activities = 61 %
Question 4). Solution :- Delivery cycle time = Throughput time + Wait time.
= 8.7 + 16.6
= 25.3 Days.
Conclusion :- Delivery cycle time = 25.3 Days.
Question 5). Solution :-
New Throughput time = Inspection time + Process time + Move time + Queue time.
= 0.5 + 3.4 + 1.3 + 0
= 5.2 Days.
New Manufacturing cycle efficiency (MCE) = Process time / New Throughput time
= 3.4 / 5.2
= 0.65 i.e., 65 %
Conclusion :- New Manufacturing cycle efficiency (MCE) = 65 %.