Practice Exercise 10-3 Tamarisk Industries Inc. started construction of a manufa
ID: 2591749 • Letter: P
Question
Practice Exercise 10-3 Tamarisk Industries Inc. started construction of a manufacturing facility for its own use at an estimated cost of $9,000,000 on January 1, 2017. Tamarisk expected to complete the building by December 31, 2017. Tamarisk's debt, all of which was outstanding during the construction period, was as follows. ·Construction loan-11.00% interest, payable semiannually, issued December 31, 2016; $4,500,000 · Long-term loan #1-10.00% interest, payable on January 1 of each year. Principal payable on January 1, 2019; $1,350,000 · Long-term loan #2-12.00% interest, payable on December 31 of each year. Principal payable on December 31, 2025; $3,150,000 Assume that Tamarisk completed the facility on December 31, 2017, at a total cost of $9,270,000, and the weighted-average amount of accumulated expenditures was $6,120,000 Compute the avoidable interest on this project. Use interest rates rounded to 2 deci a laces, e g 7.58% and round fina answer to decima places, e 9- 2 Avoidable Interest s Compute the depreciation expense for the year ended December 31, 2018. Tamarisk estimated the facility's useful life to be 25 years with a salvage value of $900,000. Tamarisk elected to depreciate the facility on a straight-line basis. Depreciation ExpenseExplanation / Answer
Answer:-
Calculation of Avoidable Interest:-
Calculate Interest on Remaining loan up to weighted average expenditure total using "Weighted Average Rate"
Totals
$1620000
$6,120,000
11.40%
184680
$679,680
Calculation of Weighted for non-specific loans:-
Weighted Average Rate = ($513,000÷$4,500,000)×100 = 11.40%
Therefore, the Avoidable interest = $679,680
Because, Avoidable interest is lower than actual interest use Avoidable interest
Cost = $9,000,000
Interest Capitalized = $679,680
Total Cost = $9,679,680
Depreciation Expense = ($9,679,680 - $900,000) ÷ 25 years
= $8779680 ÷ 25 years
= $351,187
Therefore, the Depreciation expense = $351,187
Weighted Average Accumulated Expenditure Interest Rate Avoidable Interest Calculate Interest on loan specifically for Construction $45,000,000 11% $495,000Calculate Interest on Remaining loan up to weighted average expenditure total using "Weighted Average Rate"
Totals
$1620000
$6,120,000
11.40%
184680
$679,680
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.