https View Favorites Tools Help ebet-Blackboard Bank N Netflix yelugidoas MGR ACCT 2060 CH n HW EX 11-3 FALL 2017 Management of Mmel Rhen AG of Kain, Germany would lke to reduce the amount of ome between when a customer end when the order is shipped For the firsi quanter of operations durng the current year the folowing dete were reported places an order 0.2 days 2, days 1.2 days 3. day Move tine Required t Compute the throughout me. Round your answer to 1 decmal place 2 Compute the manufactung cycle efficency (MICE) for the quate Round your percentage answer to nearest whole percent) 3 whst peecerntage of the troughout ome was spent in non-valus-added actveties? Round your percentage answer to nearest 4 Compute the delivery cycle sme (Round your intermedate caliculations and final answer to 1 decimal place) 5. If by using Lean Production al queue time during p calculations Round your percentage answer to nearest whole enc pencent TOSHIBA

Explanation / Answer

= Process time + Inspection time + move time + Queue time

                               = 2.6 + 0.2 + 1.2 + 3.6

                               = 7.6 days

                                                = 2.6 / 7.6

                                                = 34%

= (Inspection time + move time + Queue time) / Throughput time

                               = (0.2 + 1.2 + 3.6) / 7.6

                               = 5.0 / 7.6

                               = 66%

                                  = 16.0 + 7.6

                                  = 23.3 days

= Process Time / (Process time + Inspection time + move time)

= 2.6 / (2.6+ 0.2 + 1.2)

= 2.6 / 4.0

= 65%