Thing Co. uses a job order costing system. At the beginning of July, the company

ID: 2605992 • Letter: T

Question

Thing Co. uses a job order costing system. At the beginning of July, the company had the following job in progress:

Job 70

$16539


During July, Thing Co. incurred the following job related costs:

Direct Materials

Direct Labour

Job 70

$2740

$1163

Job 80

12316

16294

Job 90

8248

7908


Manufacturing overhead is applied at a rate of $3.79 per $1 of direct labour cost. Jobs 70 and 90 were moved to finished goods during the month, but neither was sold by the end of the month. Job 80 is still in progress.

What would the debit to Finished Goods Inventory be for the month of July?

Select one:

a. $36598

b. $115214

c. $70977

d. $54438

Job 70

$16539

Explanation / Answer

Answer is: c. $70,977

Job 70 Job 90 Opening work in process $                                 16,539 Add: Direct material added during the month $                                    2,740 $                                      8,248 Add: Direct labour added during the month $                                    1,163 $                                      7,908 Add: Manufacturing overhead applied during the month $3.79*$1,163 = $4,407.77 $3.79*$7,908 = $29,971.32 Total manufacturing cost $                           24,849.77 $                              46,127.32