Use the following info for 15 and 16. . The firm has the following projects avai
ID: 2625012 • Letter: U
Question
Use the following info for 15 and 16. . The firm has the following projects available to them:
Project IRR Cost NPV at 9%
A 18% $4,000,000 1,000,000
B 16% $1,000,000 200,000
C 14% $5,000,000 900,000
D 12% $2,000,000 400,000
E 10% $3,000,000 100,000
15. Which set of projects would maximize shareholder wealth if they have a capital budget of $7,000,000?
16. Suppose it can raise the following amounts at different costs of capital. Which set of projects would maximize shareholder wealth?
WACC Amount Raised
9% $10,000,000
11% $12,000,000
13% $15,000,000
18. Which of the following is an example of a timing option?
a. A company has the option to invest in a project today or to wait a year.
b. A company has the option to back out of a project that turns out to be unproductive.
c. A company pays a higher cost today in order to be able to reconfigure the project
Explanation / Answer
15. c
16.13% $15,000,000
18.a. A company has the option to invest in a project today or to wait a year.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.