Three bidders for a satellite system have given the following offers: Bidder A F
ID: 2626554 • Letter: T
Question
Three bidders for a satellite system have given the following offers:
Bidder A
First payment: $100m at the start
Second Payment: $250m at the beginning of second year
Third payment: $250m at the end of third year
Final payment: $400m on completion at the end of 4th year.
Bidder B
First payment: $ 200m at the start
Second Payment: $ 250m at the end of second year
Third payment: $ 250m at the end of third year
Final payment: $ 300m on completion at the end of 4th year.
Bidder C
First payment: No payment at start
Second Payment: $300m at the beginning of second year
Third payment: $200m at the beginning of third year
Final payment: $500m on completion at the end of 4th year.
All three bidders have been assessed to be technically compliant.
a) Assuming 8% discount +inflation rate, which bidder will you recommend to your management?
b) The annual operations &maintenance after completion is estimated to be $40 million, payable at the end of each year and with 5% annual increase thereafter.
Your customer has committed to pay $250 million annually at the end of the each year after completion, with the first payment at the end of 5th year from start and with 5% annual increase thereafter. The discount + inflation rate is still 8%.
For the best bidder, calculate the NPV until it becomes positive.
Explanation / Answer
Answer a
Bidder C
Since the highest NPV is for bidder B at 771.6, hence bidder B should be selected
Bidder A 0 1 2 3 4.0 Net cash flows 100.0 250.0 0.0 250.0 400.0 Discounting factor 0.926 0.857 0.794 0.735 0.681 Present value of cash flows 92.6 214.3 0.0 183.8 272.2 Net present value 762.9Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.